PPAP 101: The 18 Elements Every Automotive Supplier Must Master
PPAP has five submission levels, and the difference between Level 1 and Level 5 is the difference between one signed form and opening your entire documentation file to an on-site review. The 18 elements, the five levels, and where submissions actually go wrong.
July 22, 2026 ·
Updated July 22, 2026 ·
4 min read ·
SCMEP Training Team ·
6 views
Share
Not every part needs the same paperwork before it ships. PPAP has
five submission levels, and the difference between Level 1 and Level 5
is the difference between handing a customer one signed form and
opening your entire documentation file to an on-site review.
What PPAP actually is
The Production Part Approval Process (PPAP) is an AIAG (Automotive
Industry Action Group) standard that formally proves a supplier’s
production process can consistently make parts that meet all engineering
and specification requirements — at full production rate, not just in a
lab sample. It’s one of the “core tools” required under IATF 16949, and
it sits downstream of APQP: APQP plans the launch, PPAP proves the
process actually works before mass production starts.
The 18 elements
A complete PPAP package covers 18 documented elements, including
design records, engineering change documents, process flow diagrams,
a Failure Mode and Effects Analysis, a control plan, measurement system
analysis studies, dimensional results, material and performance test
results, and initial process studies. The specific combination of
elements a customer requires depends on the submission level requested
and the part’s risk profile.
The five submission levels
PPAP submission levels
Level
What’s submitted
Level 1
Part Submission Warrant (PSW) only, to the customer
Level 2
PSW plus product samples and limited supporting data
Level 3
PSW with complete supporting data and samples — the most common default level
Level 4
PSW plus other requirements as defined specifically by the customer
Level 5
PSW with complete supporting data reviewable on-site at the supplier’s facility
Level 3 is the default most customers request unless they specify
otherwise — Level 5 is reserved for higher-risk parts or suppliers with
a track record that warrants closer scrutiny.
Where PPAP submissions actually go wrong
The most common failure isn’t missing paperwork — it’s a mismatch
between what the PPAP package claims and what the process actually does
at full production rate. A part submitted using pilot-run samples,
measured under ideal conditions, can pass PPAP and then fail to hold
tolerance once real production speed, tooling wear, and operator
variation enter the picture. Customers that catch this discrepancy
during a later audit treat it as a serious trust issue, not a paperwork
correction.
PPAP is the final exam; APQP is the planning process leading up to
it. See our related guide on APQP
for the five phases that should happen before a PPAP submission is
ever assembled.
Frequently asked questions
What is PPAP?
The Production Part Approval Process is an AIAG standard that proves a supplier’s production process can consistently make parts meeting all engineering and specification requirements at full production rate. It’s one of five required “core tools” under IATF 16949.
How many elements are in a PPAP submission?
A complete PPAP package covers 18 documented elements, including design records, process flow diagrams, FMEA, control plan, measurement system analysis, and dimensional and test results.
What are the PPAP submission levels?
There are 5 levels, ranging from Level 1 (Part Submission Warrant only) to Level 5 (full documentation reviewable on-site at the supplier). Level 3, which includes complete supporting data and samples, is the most common default.
What’s the most common PPAP mistake?
Submitting a package based on pilot-run or ideal-condition samples that doesn’t reflect what the process actually produces at full production rate, where real-world variation, tooling wear, and operator differences can push parts out of tolerance.